How Long Do Bulk T-Shirts Take to Make?
By The Velocity Wear Team
Bulk t-shirts take 10 to 15 working days to produce, counted from the moment artwork is approved, with delivery transit on top. That is roughly two to three calendar weeks of manufacturing. What sits before it is the part buyers underestimate: quoting, artwork preparation, a proof round and, if you want one, a sample. Plan the whole chain, not the production window.
When does the clock actually start?
At approval. Not when you enquire, not when you pay, and not when you send a logo. Production begins once the artwork has been prepared, proofed and signed off, because screens, embroidery files and colour references are all built from the approved version. A buyer who sends a logo on Monday and approves the proof on Friday has lost four days that were never part of the 10 to 15. You can see the product range on our wholesale t-shirts page and the quantity tiers on the pricing page.
What happens during those 10 to 15 days?
The blanks are pulled in the sizes and colour you ordered. Screens are burned per colour, or the embroidery file is digitised and stitched out on a test piece, or the DTF transfers are printed and cured. Then the run is decorated, checked, cured or pressed, folded, labelled and bagged. Quality checking is a real stage rather than a flourish: it is where a misaligned print or a mismatched size box gets caught before it becomes your problem.

What adds days to the timeline?
Four things, in rough order of how often they bite. Slow artwork sign-off, which is entirely within your control. A sample round, which adds its own production and transit before the bulk run starts. Multiple decoration methods on one garment, because an embroidered chest and a printed back are two passes. And a split delivery across several addresses, which adds handling rather than manufacturing. None of these are unusual; they just need to be in the plan from the start.
How far ahead should you order for a fixed date?
Count back from the date something has to be worn. Add transit for your market, then 15 working days rather than 10, then a week of float for proof revisions, then a sample round if the order matters enough to check. For most buyers that is six to eight weeks before the event, and for anything in a seasonal peak it should be more. Ordering earlier also gives you room to reach a better quantity tier, since discounts rise up to 35% with volume and a rushed order rarely has time to be consolidated. Delivery times and transit covers the part after production ends.
Can anything be done faster?
Some of it. Sending print-ready vector artwork removes the preparation delay entirely, approving the proof the same day removes another, and choosing a single decoration method on a single position keeps the run to one pass. What does not compress is the manufacturing window itself. If your date is genuinely tight, the honest move is to simplify the order rather than to hope. Artwork setup lists what to send to skip the slowest step.
What does a realistic calendar look like?
Take a shirt needed on the first of next month. Transit before that, and 15 working days of production before transit, puts artwork approval roughly five weeks out. A proof round with one revision sits a week earlier again. If a sample is involved, that is its own production and shipping ahead of everything. So the enquiry that produces shirts on the first is the one sent about two months before, not two weeks. Buyers who work back through those stages rather than asking how fast the whole thing can go almost never have a problem with the date.