Ordering Tracksuits for Black Friday
By The Velocity Wear Team
For tracksuits you intend to sell across Black Friday, the stock has to land a fortnight before the promotion opens rather than during it. That puts artwork approval in the first half of October: 10 to 15 working days to build, transit on top, and a buffer for photography and listing the product before a single customer can add it to a basket.
How far back does promotion week push the order?
Further than most people assume, because the delivery date is not the real deadline. You cannot photograph stock you do not have, and a product page without genuine photographs converts badly during the one week of the year when everybody is comparing. Leave two weeks between delivery and going live, then count build and transit backwards from there.
That arithmetic lands in early October for a late-November promotion. Started on time it is a comfortable timeline. It only feels tight if the work begins in November.
How many sets should be on the shelf?
More than instinct suggests if the set is your discount hero, and fifty is the floor per design rather than a target. Volume moves the set price by up to 35% as quantity rises, so the margin that funds a promotional discount is far easier to find at three hundred sets than at fifty. Check where your quantity sits on the price bands before you fix the discount.
Sizing is the other half of it. A promotion clears the middle sizes first and leaves the extremes behind, so weight the size run towards the middle instead of splitting it evenly. Sizes mix freely inside the fifty, which means getting this right costs nothing.
Settle the discount and the quantity together rather than one after the other. Your cost is fixed by the band you buy in, so a promotion planned at thirty per cent off means working backwards from a cost that only exists at a certain volume. Choosing the headline number first and the order size afterwards is how a promotion ends up losing money on its best-selling line.

Where do these orders usually slip?
- Artwork approved late because the campaign copy and the garment design are signed off by different people.
- A colourway chosen to match a campaign rather than what the mill holds, which adds dye time.
- No sample, so the first sight of the finished product is the delivery itself.
- Photography booked for the same week the stock lands, with no allowance for it landing a day late.
None of those are production failures, and every one of them is avoidable in October. Ordering a £150 sample early clears two at once, since the fee is credited against the bulk order and a physical set gives the studio something to shoot before bulk arrives.
Plan for the week afterwards as well. Returns from a discount week arrive through December, and a set sold as two garments comes back as two garments. Sizing published from a measured sample rather than a generic chart is the least expensive way to keep that number down.
Can a late order still make the week?
It can, provided you cut the variables. One colourway, one decoration, stock fabric, artwork already signed off. Our wholesale tracksuits start at $53 a set at the fifty-set minimum, and the minimum does not shift because the timeline did. What shifts is how much you can afford to get wrong.
If it genuinely will not fit, sell the set on pre-order rather than shipping something rushed. Setting the expectation honestly costs less than a wave of refunds, and managing fulfilment and shipping times covers how to word it on the page.